📥 Inputs
Enter Production Rate As:
How many units does your crew install in one day?
How many units does one worker install per hour?
How many labor-hours to install one unit?
How many crew-days for the quantity above?
$/hr
Fully burdened rate (use Crew Burden Calculator if unsure)
📊 All Conversions
Production Rates
Labor-hours per unit
0.040 MH/SF
Units per labor-hour
25.0 SF/MH
Units per man-day
200 SF/man-day
Units per crew-day
400 SF/crew-day
For Your Quantity
Crew-days to complete
2.5 days
Total labor-hours
40 MH
Cost
Total labor cost
$1,920
Cost per unit
$1.92 /SF
Daily crew cost
$768 /day